Skip to main content
Education

Transforming Learning Spaces at University of Leicester

Project Details

  • Client
    University of Leicester
  • Location
    Bennett Building, University of Leicester
  • Year
    2021

Background

The project started with establishing an internal hoarding to minimise disruption to university activities. Limited site access led to the innovative solution of removing windows in both lecture theatres for material transport.

Communication was crucial throughout this complex project. Regular site meetings allowed our team to adapt swiftly to project demands. Unexpected challenges, such as the discovery of asbestos in the theatre’s risers and defective screed on the terracing floor, were promptly addressed. Asbestos consultants were engaged, and the problematic screed was replaced, involving intricate manual labor due to access constraints.

In both theatres, each step was re-shuttered, and liquid screed was pumped in to form new stairs. The introduction of 24-hour working helped mitigate delays. Our proactive approach ensured these issues caused minimal project disruption.

01 – Lecture Theatre

02 – Lecture Theatre

Solution

Seamless Execution Achieved

Despite the challenges encountered, such as the screed replacement and asbestos discovery, both lecture theatres opened on time for the university’s new term. The project’s completion to an exceptionally high standard has led to further discussions about additional work with the client, underlining Eden EMC’s commitment to quality, adaptability, and client satisfaction.

  • Well-designed bright seating area

  • Well-designed bright seating area

  • Well-designed bright seating area

  • Well-designed bright seating area

  • Well-designed bright seating area

  • Well-designed bright seating area

    Result

    Success through planning

    The project started with establishing an internal hoarding to minimize disruption to university activities. Limited site access led to the innovative solution of removing windows in both lecture theatres for material transport.

    Communication was crucial throughout this complex project. Regular site meetings allowed our team to adapt swiftly to project demands. Unexpected challenges, such as the discovery of asbestos in the theatre’s risers and defective screed on the terracing floor, were promptly addressed. Asbestos consultants were engaged, and the problematic screed was replaced, involving intricate manual labor due to access constraints.

    In both theatres, each step was re-shuttered, and liquid screed was pumped in to form new stairs. The introduction of 24-hour working helped mitigate delays. Our proactive approach ensured these issues caused minimal project disruption.

    Planning

    Would you like to know more about this project?