Project Details
-
ClientJayhems Limited
-
LocationHoliday Inn, Bournemouth
-
Year2023
Background
Eden EMC recently had the privilege of refurbishing the Holiday Inn in Bournemouth for Jayhems Limited. This complex project was executed within an operational hotel, necessitating detailed coordination between our site manager and the hotel manager.
With the hotel encompassing six floors of bedrooms, an open lobby, gym and restaurant, strategically phasing the project was imperative to minimise guest disruption.
01 – 108 Bedrooms
02 – Restaurant
Solution
The refurbishment was organised into six phases, beginning with the complete overhaul of 108 bedrooms across six floors. Working in sync with the hotel’s operations, we tackled 18 bedrooms per floor in three-week intervals, starting from the top floor and working downwards.
The process involved stripping out existing bedrooms and bathrooms, installing new bathroom subfloors, tiling, carpets, lighting, and case goods in the bedrooms. Our in-house decorating team then added the final touches with new paint and finishes. Corridor carpets were replaced, and walls were redecorated during each phase as well.
Concurrently, during the final bedroom phase, we embarked on the complete refurbishment of the open lobby and restaurant. Collaborating closely with the hotel manager, we kept select areas functional for guest services like breakfast. This included installing hoardings before removing large ceiling bulkheads, forming new bulkheads, and spraying the ceiling.
We then added new floor tiles, ‘Amtico’ floor coverings, specialist joinery, booth seating, and a servery unit. Other works in this phase encompassed fitting a new illuminated back bar, refurbishing the existing bar and reception front, creating a soundproof meeting room, and establishing a private dining area within the restaurant with new sliding glass doors.
Additional tasks included transforming an existing meeting room into a gym, involving a complete strip-out, electrical rewire, new ceiling, flooring, and installation of full-height mirrors for a premium finish.
Result
Operating in a live hotel environment presented unique challenges, but through effective communication and collaboration with the hotel management, Eden EMC successfully completed the project on time, snag-free, and to the high standard our client expects.